For the new university campus of Howest in Kortijk, Peikko's DELTABEAM® solution was chosen to be able to create slim floors and keep a lot of flexibility in the layout.

Peikko delivered more than 1,200 meters of DELTABEAM® composite beams for this project.  

For DELTABEAM® excellent preparation is needed and the engineering is very important. When the engineering is finalized, the base for a very fast building system is established. At the same time there are benefits for the installation of HVAC, since there is a lot more usuable height available when working with DELTABEAM®.

Tom Verplancke, site manager for Monument Vandekerckhove

Projekt information

Etager:
5
Projektudvikler:
Howest, Hogeschool West-Vlaanderen
Enterprenør:
Monument Vandekerckhove
Konstruktionsingeniør:
ABDM
Arkitekt:
RAU
Leveringsår:
2018
Afleveringsår:
2019