For the raising of the sedimentation basin within the sewage treatment plant in Eindhoven, the precast elements are connected to each other in a fast and efficient way with the Peikko SUMO® wall shoe connection. 

This dry connection consists of a SUMO® Wall shoe cast in one element and an HPM® anchor bolt cast in the other element. Together this forms the wall shoe joint that absorbs tensile loads. To provide protection against corrosion, the connections are galvanized in this project.

Projekt information

Projektudvikler:
Waterschap De Dommel
Enterprenør:
Van Boekel Bouw & Infra
Elementleverandør:
Haitsma Beton
Leveringsår:
2019
Afleveringsår:
2020